Need a schedule of condition? Get a fee proposal the same working day.
Fast Track Quotation →Party Wall Notice
A party wall notice is the formal written document required by the Party Wall etc. Act 1996. It must be served on every adjoining owner before notifiable works start. Without a valid notice, the rest of the statutory process cannot begin and the building owner exposes themselves to injunction risk.
The notice is deliberately structured, because its contents, timing and method of service are all capable of invalidating the process if they are wrong. This page covers when a notice is required, how it must be served, and what happens afterwards. For the broader legislation, see the Party Wall etc. Act 1996 guide.
What It Is
The opening statutory document of the Party Wall Act process in England and Wales.
When It Is Served
Before any notifiable works start, with at least one or two months' statutory notice depending on the section.
Why It Matters
A defective or late notice invalidates the process and can stop the project under injunction.
The key point
Planning permission is not a party wall notice. The two run on separate tracks, and a project can be perfectly lawful from a planning point of view and still be exposed to injunction for having missed the Party Wall Act.
If you are drafting or have received a party wall notice, send it over. We will check its validity and advise on the correct response within the 14 day window.
Contact us →When a notice is required
The following are the main situations in which a notice is required, though the list is not exhaustive — a surveyor should confirm whether your specific works trigger the Act.
- Before carrying out works on or to a party wall, such as cutting in to support a beam.
- Before building a new wall on or astride the line of junction between two properties.
- Before excavation within three metres of a neighbouring building below the level of their foundations.
- Before excavation within six metres of a neighbouring building that cuts below a 45-degree line from the base of their foundations.
- Before demolition, underpinning, raising or rebuilding of any party structure.
For detail on the excavation triggers see the section 6 guide and the 3 metre rule. For building at the boundary specifically, see the line of junction notice page.
How the notice must be served
The Act specifies the permitted methods of service. Any of the following is acceptable:
- By hand to the adjoining owner at the property.
- By post to the adjoining owner at their last known address, including where they do not live at the adjoining property.
- Where appropriate, by delivery to the registered office of a corporate owner.
- Where the adjoining owner cannot be identified, by fixing the notice conspicuously to the adjoining property.
Keep evidence of service. Proof of posting, a dated photograph of a notice fixed to the property, or an acknowledged receipt is often decisive if validity is later questioned.
How the adjoining owner may respond
Once validly served, the adjoining owner has 14 days to respond. The outcomes are limited.
Consent
Written consent to the notice avoids the need for a formal award. Keep the consent on file as evidence of compliance with the Act.
Dissent or silence
A written dissent, or silence for 14 days, is treated as a deemed dispute. Surveyors must be appointed and a Party Wall Award produced.
For what follows when agreement is not reached, see party wall award. For the everyday term used to describe the outcome, see party wall agreement.
Getting the timing right
Statutory notice periods run from the date of valid service. For section 2 works on or to a party wall the period is two months. For section 1 and section 6 it is one month. The 14 day response period runs concurrently within that notice period, not after it.
Plan backwards from the intended start on site date. If the construction programme assumes a start within a few weeks, and the notice still has to be drafted and served, the project is on a collision course with the Act.
Common mistakes
- Serving only the freeholder when leaseholders with more than a year unexpired are also adjoining owners.
- Serving by email only, where the Act does not expressly provide for electronic service.
- Running the notice period from the date of drafting rather than the date of proper service.
- Describing the works too vaguely, so that the notice is open to challenge for invalidity.
- Starting site preparation works during the statutory notice period.
Drafting or responding to a party wall notice?
The notice is the first serious moment in the party wall process. Getting it right is cheaper than fixing it later, and responding to it carefully is cheaper than reacting too fast.
See our party wall surveyor service or compare this page with the guides on the Party Wall Act, party wall award, and party wall agreement.
Related knowledge
Compare this article with the nearest matching pages if you want to follow the topic into related surveying questions.
Plain-English guide to the Party Wall etc. Act 1996 — what the legislation covers, which works are notifiable under sections 1, 2 and 6, how the notice and award process runs, the role of the surveyor, and the consequences of proceeding without compliance.
Plain-English guide to party wall agreements under the Party Wall etc. Act 1996 — what the agreement is, when one is needed, what it contains, and the process of getting one in place through written consent or a formal Award.
Plain-English guide to party wall awards under the Party Wall etc. Act 1996 — when an award is required, what it contains, how it is produced by appointed surveyors, how it is appealed, and how it governs works on site.
Plain-English guide to section 6 of the Party Wall etc. Act 1996 — the two excavation triggers (3 metre and 6 metre rules), when notice is required, what it must contain, and what happens after service including the party wall award process.
Key Services
Need a surveyor rather than another article?
If this article relates to a live property issue, one of these service pages is likely to be the most useful next step.
Lease-end claims
Dilapidations
Landlord and tenant advice on schedules, quantified demands, lease interpretation, and negotiated settlement.
Explore DilapidationsNeighbourly matters
Party wall matters
Notices, adjoining owner response, schedules of condition, awards, and practical support before works start.
Explore Party wall mattersLease protection
Schedules of condition
Condition recording for lease commencement, pre-works evidence, and later protection against dispute over pre-existing condition.
Explore Schedules of condition
