Knowledge

Need a schedule of condition? Get a fee proposal the same working day.

Fast Track Quotation →

The Party Wall Act 3 Metre Rule

The 3 metre rule is the most commonly encountered trigger for section 6 of the Party Wall etc. Act 1996. It requires a building owner to serve a formal notice on any adjoining owner where proposed excavation is both within three metres of the neighbour's building and deeper than the bottom of their existing foundations.

It catches many extension and basement projects where the building owner assumes the works are too modest to require a notice. For the wider framework, see the Party Wall etc. Act 1996 and the section 6 guide.

What It Is

A statutory trigger requiring notice before excavation within 3 metres of a neighbour's building at a depth below their foundations.

When It Applies

Rear and side extensions, basements, lightwells, lift pits and underpinning are the everyday examples.

Why It Matters

Ignoring the rule can bring works to a halt under injunction and expose the building owner to damages claims.

The key point

The three metres is measured from the neighbour's building, not from the boundary line. If the neighbour sits hard against the boundary, almost any excavation along that flank will be caught.

Send us the proposed foundation drawings and a site plan. We will confirm whether the 3 metre rule applies and draft the section 6 notice.

Contact us

How the rule works

The rule combines a distance test and a depth test, and both must be satisfied for the notice requirement to bite.

Distance test

The excavation must fall wholly or partly within three metres, measured horizontally, of any part of the adjoining owner's building or structure.

Depth test

The excavation must extend to a depth lower than the bottom of the neighbour's existing foundations. A drawing showing a conservative assumed depth is usually enough.

When the 3 metre rule applies

The following are typical examples:

  • Any excavation within three metres of an adjoining owner's building or structure that goes deeper than the bottom of their existing foundations.
  • Works for basement construction, lift pits, lightwells and underpinning along a neighbouring boundary.
  • Foundations for rear or side extensions where the proposed trenches are deeper than the neighbour's.
  • New retaining walls and drainage runs that cut below adjoining foundations within the three metre zone.
  • Demolition works where subsequent excavation will fall within the statutory geometry.

If the proposals include deep piles or a basement, the section 6 guide should be read alongside this one, because the 6 metre rule frequently applies as well.

What the notice must contain

A section 6 notice — required whether the 3 metre or 6 metre trigger applies — is a formal statutory document. Defects in content or service can invalidate it and force the notice to be re-served.

  • The name and address of the building owner.
  • The address of the site on which the works are proposed.
  • A description of the proposed excavation, with plans and sections.
  • The proposed depth of the excavation and its position in relation to the neighbouring building.
  • The proposed start date, giving at least the statutory one month's notice.

For the general rules on party wall notices, see the party wall notice guide.

What happens after service

The adjoining owner has 14 days from service to respond. They can consent in writing, dissent in writing, or do nothing — which the Act treats as a deemed dispute. In a dispute, surveyors are appointed and a party wall award is drawn up before excavation can start.

The Award typically records the existing condition of the neighbour's property, sets the manner and timing of the excavation, and provides a mechanism for resolving any damage that might be caused.

How it differs from the 6 metre rule

The 3 metre rule is the most commonly quoted, but section 6 has a second limb. The 6 metre rule applies where excavation within six metres of an adjoining building would cut below a line drawn down at 45 degrees from the base of their foundations. It typically catches deeper projects such as piled basements and lift pits.

Both rules can apply to the same project. Where they do, the notice still only needs to be served once, but the plans must demonstrate the relationship between the proposed works and both geometric tests.

Common mistakes

  • Assuming the rule only applies to basements. Shallow trenches for extension foundations can be caught just as easily.
  • Measuring the three metres from the wrong point — it is measured from the nearest part of the neighbour's building, not the boundary.
  • Treating the neighbour's ground level as a proxy for their foundation depth. The correct reference point is the bottom of their foundations.
  • Skipping the notice because the neighbour has been told verbally. Verbal warnings are not statutory service.
  • Starting excavation during the 14 day response period, which turns a procedural issue into an injunction risk.

Unsure whether the 3 metre rule applies to your project?

If your drawings show excavation anywhere along a boundary, a short review against the Act before tender avoids the programme colliding with the statutory notice period.

See our party wall surveyor service or compare this page with the guides on the section 6 of the Act, party wall notice, and line of junction notice.

Related knowledge

Compare this article with the nearest matching pages if you want to follow the topic into related surveying questions.

The Party Wall etc. Act 1996

Plain-English guide to the Party Wall etc. Act 1996 — what the legislation covers, which works are notifiable under sections 1, 2 and 6, how the notice and award process runs, the role of the surveyor, and the consequences of proceeding without compliance.

Party Wall Act Section 6

Plain-English guide to section 6 of the Party Wall etc. Act 1996 — the two excavation triggers (3 metre and 6 metre rules), when notice is required, what it must contain, and what happens after service including the party wall award process.

Party Wall Notice

Plain-English guide to the party wall notice under the Party Wall etc. Act 1996 — when it is required, how it must be served, statutory notice periods, and the options open to the adjoining owner on receipt.

Party Wall Award

Plain-English guide to party wall awards under the Party Wall etc. Act 1996 — when an award is required, what it contains, how it is produced by appointed surveyors, how it is appealed, and how it governs works on site.

Key Services

Need a surveyor rather than another article?

If this article relates to a live property issue, one of these service pages is likely to be the most useful next step.

Lease-end claims

Dilapidations

Landlord and tenant advice on schedules, quantified demands, lease interpretation, and negotiated settlement.

Explore Dilapidations

Neighbourly matters

Party wall matters

Notices, adjoining owner response, schedules of condition, awards, and practical support before works start.

Explore Party wall matters

Lease protection

Schedules of condition

Condition recording for lease commencement, pre-works evidence, and later protection against dispute over pre-existing condition.

Explore Schedules of condition